Completed Projects

Completed Projects

Completed Projects

The new parking garage and student union kitchen remodel are now complete and operational campus-wide, and the infrastructure is complete and fully functional. These improvements to the Rocklin campus were made possible by Measure E.

On this page, you can find the following completed projects:

Four level parking structure with vertical Sierra signage

Parking Garage

486,700 gross square feet, 101,000 square foot footprint, 5 levels
$49.9M final construction cost
Notice of completion: July 2021
Measure E funded

  • 1,501 parking spaces
  • 20 active electrical vehicle stations with 68 expansion stations
  • Will address post-pandemic needs for parking on campus while helping to reduce traffic and parking impacts in the surrounding community

Watch 62-second time-lapse video of parking garage construction

Entrance to The Wolverine Cafe

Student Union Phase 1-Kitchen Renovation

$5M final construction cost
Notice of completion: February 2021
Measure E Funded

  • Original cafeteria kitchen and serving areas in Building J, Campus Center brought to current building code requirements
  • Kitchen plumbing and wiring updated
  • Air handling units replaced to improve energy efficiency
  • Generator added to support refrigerators/freezers in case of loss of power
Underground water pipes being replaced on Sierra Rocklin campus

Infrastructure Project

Construction budget: $25M
Project budget: $32.6M
Completion: Summer 2022
Measure E funded

Upsizing or replacement of utility and technology services to all existing and new buildings

  • Include electrical service, low voltage (data) service, water service (potable and non-potable), sanitary sewer, and storm water systems
  • Natural gas infrastructure will be extended to the planned new construction